What is detailed cost estimation of G+2 building | complete cost estimation of 1400 sft slab area building

Photo of author

By Shravan

Contents

What is detailed cost estimation of G+2 building | complete cost estimation of 1400 sft slab area building

In this article I will explain you the detail cost estimation of G+2 building which is consisting of 24’4”X58’0” plot size.

Cost estimation

The cost estimation is the process of determining the total money required to complete the project as per the requirements of architectural plan. The cost estimation can be determined with the help of long wall and short wall method or center line method. The long wall short wall method frequently used for perfect estimate.

In my previous articles I was explained cost estimation for 3BHK building click here to read.

Detailed cost estimation for 1000 sft slab area click here to read.

The G+2 building plan of South facing is taken for the cost estimation which is having dimensions of site are 24’4”X58’0” the Floor plans are shown in the below figure.

cost estimation plan
G+2 building typical floor plan
cost estimation building
Building 3D view

The cost estimation is determined for 1400 square feet slab area.

Cost estimation of ground floor building

The complete cost estimation of ground floor building is explained in the below table

S. No Description No Length (m) Breadth (m) Depth (m) Quantity (cu.m) Total quantity  (cu.m) Rate /cu.m Total amount ( rs )
1 EXCAVATION OF FOUNDATION 13 1.5 1.5 1.95 57.037 57.037 240 13,689
2 PCC 1:4:8   AT FOUNDATION 13 1.5 1.5 0.3 8.775 8.775 5850 51,333.75
3 BRICKWORK IN FOUNDATION 0 0
1   Rectangle portion 13 1.5 1.5 0.4 11.7 0 0
2  Trapezoidal portion 13 6.43 0 0
3  COLUMN UPTO GROUND LEVEL 13 0.3 0.3 0.6 7.02 25.15 240 6,964.80
4 FILLING IN FOUNDATION 57.0.37-25.15 23.1125 23.1125 480 11,094
5 EARTH WORK FILLING IN PLINTH LEVEL 0 0
1        BED  ROOM 1 1 3.6 3.65 0.52 6.832 0 0
2        BED ROOM 2 1 3.6 3.65 0.52 6.832 0 0
3        BATHROOM 1 2.13 1.14 0.52 1.262 0 0
4        DINING 1 3.6 1.14 0.52 2.134 0 0
5         SPACING NEAR DINING AND BEDROOM 1 1 1.17 1.44 0.52 0.876 0 0
6         KITCHEN 1 3.6 2.49 0.52 4.661 0 0
7         HALL 1 3.6 5.37 0.52 10.052 32.649 960 31,343.04
0 0
6 DPC  AT PLINTH LEVEL 13 0.3 0.3 1.17 1.17 600 702
0 0
7 BRICK MASONRY WORK AT SUPER STRUCTURE 1 55.55 0.3 3.5 58.327 0 0
DEDUCTIONS 0 0
1         DOORS & WINDOWS 6.501 0 0
2         RCC LINTEL 0.697 0 0
ACTUAL BRICK QUNATITY 51.129 300 15,339
8 SLAB 1 10.7 12.02 0.125 16.07 0 0
DEDUCTION OF STAIR CASE 1 2 3.5 0.12 0.84 0 0
ACTUAL SLAB AREA 15.23 12000 182,760
9 RCC CHAJJA 0.5265 12000 6,318
10 RCC 0 0
1    COLUMN FOOTING 13 1.5 1.5 0.6 17.55 17.55 10500 184.275
2    PLINTH BEAM 7 17.96 0.3 0.6 22.62 22.62 11400 200,070
3    ROOF BEAM 7 17.96 0.3 0.3 11.31 11.31 11400 135,771
11 STEEL 0 0
1     FOOTINGS 19.5 x  90 KGS 1755 126 221,130
2     COLUMNS 11.6 x   120 kgs 1392 126 175,392
3     PLINTH BEAM 7.65 x   110 KGS 841.5 126 106,029
4     ROOF BEAM 7.65 x   110 KGS 841.5 126 106,029
5     ROOF SLAB 16.07 x   80 KGS 1285.6 126 161,985.60
6     STAIR CASE 9.08 x   110 KGS 998.8 126 125,848.80
12 FLOORING TILES 0 0
1    BEDROOM 1 & 2 2 3.6 3.65 26.28 0 0
2    BATHROOM 1 2.13 1.14 2.428 0 0
3    DINING 1 3.6 1.14 4.104 0 0
4    SPACING NEAR DINING AND BEDROOM 1 1 1.17 1.44 1.684 0 0
5    KITCHEN 1 3.6 2.49 8.964 0 0
6    HALL 1 3.6 5.37 19.332 0 0
OVERALL 62.792 2400 164,256
13 PARAPET WALL 0 0
LENGTH    WISE 2 10.7 0.2 1 4.28 0 0
BREADTH WISE 2 12.02 0.2 1 4.8 0 0
TOTAL 9.08 300 2724.3
14 STAIR CASE 0 0
1     RCC  (1:1.5:3) 0 0
          BASE ON TOE WALL 1 2 0.35 0.45 0.315 0 0
          WAIST SLAB 2 2.96 1 0.12 0.71 0 0
          LANDING SLAB 1 2 1 0.18 0.72 0 0
          OVERALL 1.745 0 0
2     BRICKWORK IN CM (1:5) FOR STEPS 22 1 0.018 0.412 0.412 0 0
3      PLASTERING 10.277 0 0
          OVERALL 12.43 12000 144,264
15 PLASTERING 243.075 0 0
INSIDE WORK 139.829 0 0
OUTSIDE WORK 103.055 0 0
ROOF 485.959 210 102,051.39
OVERALL 0 0
16 FINISHING WORKS 16.57 0 0
TRANSPORTATION & LABOUR CHARGES 652.2 0 0
OVERALL 668.7 240 160,488
OVERALL ESTIMATION COST 0 2194650
17 LUMPSUM WORKS 0 173,610
ELECTRICAL WORKS   7.5% OF OVERALL COST
OVERALL ESTIMATION OF GROUND FLOOR 2491260

For the ground floor approximately it is required 2491260 Indian rupees for the building construction.

Cost estimation of first floor and second floor building

The complete cost estimation of first floor and second floor building is explained in the below table

S. No Description No Length (m) Breadth (m) Depth (m) Quantity (cu.m) Total quantity  (cu.m) Rate /cu.m TOTAL AMOUNT ( rs )

1

BRICK MASONRY WORK AT SUPER STRUCTURE 1 55.55 0.3 3.5 58.327
DEDUCTIONS
1         DOORS & WINDOWS 6.501
2         RCC LINTEL 0.697
ACTUAL BRICK QUNATITY 51.129 300 15,339

2

SLAB 1 10.7 12.02 0.125 16.07 0 0
DEDUCTION OF STAIR CASE 1 2 3.5 0.12 0.84 0 0
ACTUAL SLAB AREA 15.23 12000 182,760

3

RCC CHAJJA 0.5265 12000 6,318

4

RCC 0 0
1   ROOF BEAM 7 17.96 0.3 0.3 11.31 11.31 11400 135,771

5

STEEL 0 0
1   ROOF BEAM 7.65 x   110 KGS 841.5 126 106,029
2   ROOF SLAB 16.07 x   80 KGS 1285.6 126 161,985.60
3   STAIR CASE 9.08 x   110 KGS 998.8 126 125,848.80

6

FLOORING TILES 0 0
1    BEDROOM 1 & 2 2 3.6 3.65 26.28 0 0
2    BATHROOM 1 2.13 1.14 2.428 0 0
3    DINING 1 3.6 1.14 4.104 0 0
4    SPACING NEAR DINING AND BEDROOM 1 1 1.17 1.44 1.684 0 0
5    KITCHEN 1 3.6 2.49 8.964 0 0
6    HALL 1 3.6 5.37 19.332 0 0
OVERALL 62.792 2400 164,256

7

PARAPET WALL 0 0
LENGTH    WISE 2 10.7 0.2 1 4.28 0 0
BREADTH WISE 2 12.02 0.2 1 4.8 0 0
TOTAL 9.08 300 2724.3

8

STAIR CASE 0 0
1     RCC  (1:1.5:3) 0 0
          BASE ON TOE WALL 1 2 0.35 0.45 0.315 0 0
          WAIST SLAB 2 2.96 1 0.12 0.71 0 0
          LANDING SLAB 1 2 1 0.18 0.72 0 0
          OVERALL 1.745 0 0
2     BRICKWORK IN CM (1:5) FOR STEPS 22 1 0.018 0.412 0.412 0 0
3      PLASTERING 10.277 0 0
          OVERALL 12.43 12000 144,264

9

PLASTERING 243.075 0 0
INSIDE WORK 139.829 0 0
OUTSIDE WORK 103.055 0 0
ROOF 485.959 210 102,051.39
OVERALL 0 0

10

FINISHING WORKS 16.57 0 0
TRANSPORTATION & LABOUR CHARGES 652.2 0 0
OVERALL FINISHING WORK CHARGES 668.7 300 200,631
OVERALL ESTIMATION COST 0 1347978

11

LUMPSUM WORKS 0 0
ELECTRICAL WORKS   7.5% OF OVERALL COST 0 94,359
OVERALL ESTIMATION OF FIRST FLOOR 0 1442337

For the first floor  and second floor approximately it is required 1442337 Indian rupees for the building construction.

Other cost estimates

Other cost estimates related to water supply, sanatory,  stair grills, balcony grills, septic tank are shown in the below calculation.

Provision of sanitary and water supply arrangements

130000

Stair case with grills

90000

Balcony Grills

100000

Septic Tank

30000

Abstract of cost estimation

the final abstract of cost estimation was shown in the below table for the G+2 building cost estimation.

Ground Floor

2491260

First Floor

1442337

Second floor

1442337

Other estimates

350000

Total

5,725,934

for the ground floor it is required approximately 2491260 Indian rupees, for the first and second floor it is required 1442337+1442337 and other estimates required 350000 Indian rupees.

Conclusions of cost estimation for G+2 building

Well now the above explained concepts are related to the complete cost estimation of G+2 building structure. For the ground floor it is required approximately 2491260, for the first and second floor it is required 1442337+1442337 and other estimates required 350000 Indian rupees.

Previous five blogs

  1. Complete Dead load calculation of G+1 building click here to read.
  2. Cost estimation of marbles and tiles for 1000sft and 1500sft area click here to read.
  3. How to calculate volume of concrete per cubic meter click here to read.
  4. What is slab different types of slabs click here to read.
  5. What is minimum and maximum center to center distance between RCC columns click here to read.

Please follow my YouTube channel for more information regarding civil engineering concepts.

If you have any quarries regarding this article please feel free to reach us at contact us page.

Thank You

Your Shravan

Have a good day.